Power shut down in Jammu

Power supply to remain affected in Jammu

In order to carry out the work for erection of beam structures in existing bay and stringing of conductor of 11 KV O/G feeder, Rakh Muthi at 33/11 KV Receiving Station  Burmal by M/s IRCON International Ltd under Cluster-IV R-APDRP Part-B, the shutdown of 33 KV Jourian I/C line emanating from 132/33 KV Grid Station Akhnoor on December 27, 2015 from 09:30 AM to 04:30 PM is allowed.

          The areas to be affected during the shutdown period included Burmal, Devipur, Rakh Muthi, Sohal Bhalwal, Jourian, Sohal, Rakh Malal and Essential 11 KV feeder of BSF, MES & PHE.

Similarly, to carry out the work for PCC Pole insertion and 11 KV reconductoring  as 11 KV (K-02) feeder is passing under the 33 KV New Kartholi feeder near 33/11 KV Receiving Station Katholi (EPIP), the shutdown of 33 KV Kartholi (EPIP) feeder on December 27, 2015 from 09:00 AM to 01:00 PM  is allowed.

The areas to be affected during the shutdown period included Industrial area of EPIP Kartholi and Bari Brahmana.