Power shutdown in Jammu

Power supply to remain affected in Jammu

In order to carry out development works by M/s IRCON International Ltd., 33 KV Line PC-I Line emanating from 132/33 KV Grid Station Pouni Chak shall remain under shut down on January 20, 24, 29 and 31, 2016 from 9 a.m. to 5 p.m. for installation of various equipments by M/s IRCON under Cluster-II, R-APDRP Part-B.
The areas to be affected during the shutdown period are Talab Tillo, Gole, Panjpir, Gas Plant, Camp, Mandli, Seora,Sunder Nagar, Gole Gujaral, Khessia, Polgal, Bhagatpur, Repar Sani and adjoining areas.
Meanwhile, in order to carry out the work by M/s IRCON International Ltd the 33 KV Line G-7 feeder at Tap point Transport Nagar to Bathandi emanating from 220/132/33 KV Grid Station Gladni shall remain under shut down on January 20, 22, 24, 26, 28, 30 and February 1, 3, 5, 7,9, 11, 13 and 15, 2016 from 10 a.m. to 4 p.m.
The areas to be affected during the shutdown period are Transport Nagar and Bathandi.